WSDOT SR 9 176th St SE to SR 96 Widening Project Presentation

September 19, 2024

Agenda

  • Introductions
  • Project Overview
  • Roundabouts Configurations
  • Major Milestones
  • Questions / Discussions

Introductions

  • Engineer Manager: Curt Winningham P.E.
  • Project Engineer: Kyengo Ndile P.E.
  • Communication Manager: Eric Zackula

Project Overview

To relieve congestion along State Route 9:

  • Widen SR 9 between 176th SE and SR 96/Broadway Avenue to create two lanes in each
    direction.
    • Widen both sides of SR 9 to add an additional lane for northbound traffic.
    • Reconfigure the existing corridor for southbound traffic to accommodate the additional northbound lane.
  • Replace existing signalized intersections with roundabouts at: 176th St SE, 164th St SE,
    Cathcart Way, and SR 96.

Major Milestones

  • 4/30/2024 – Submit 30% Plans & Chan Plans for review and comments.
  • 8/30/2025 – Submit 60% Plans, Estimates & Final Chan Plan for approval
  • 2/27/2026 – Submit 90% Plans, Estimates & Specs
  • 9/30/2026 – Submit 100% Plans & complete all Environmental Permits
    and Property acquisition
  • 8/19/2027 – Project Ad

Helpful Links

Meeting Video

Events

Links

To find out what’s happening in and around Clearview, we have assembled a listing of pages and links.

Your local representatives: